In effectFederal Decree by Law

UAE Energy / Oil & Gas LawFederal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid

UAE Federal Decree-Law·Federal Decree by Law No. (17) of 2022

مرسوم بقانون اتحادي في شأن تنظيم ربط وحدات إنتاج الطاقة المتجددة الموزعة بالشبكة الكهربائية

Authoritative Arabic version per the official UAE Legislation portal

Issued Date
September 26, 2022
Effective from
October 28, 2022
Articles
17
Last synced
Jun 22, 2026

Plain-language summary

  • Sets rules for connecting small renewable energy systems (solar, wind) to UAE's power grid.
  • Applies to homes, businesses, and facilities generating their own clean energy.
  • Requires technical safety standards and equipment approval before grid connection.
  • Allows owners to feed excess power back to the grid or store it.
  • Establishes how grid operators manage and monitor distributed renewable units.

Regulates the connection of distributed renewable energy production units to the electrical grid, establishing technical and operational requirements for grid i…

Synced from the official UAE Legislation portal · Plain-language summary by the LEXAI editorial team

Article-level text

Key Articles

17 articles

  1. 1

    Article 1

    Article (1) Definitions In application of the provisions of this Decree by Law, the following words and phrases shall have the meanings assigned to each of them, unless the context otherwise requires: State : United Arab Emirates. Ministry : Ministry of Energy & Infrastructure. Emirate : Any emirate of the State. Competent Authority : The ministry or local authority competent to regulate the production, distribution and supply of electricity, as the case may be. Renewable energy : Energy derived from natural sources that are replenished at a higher rate than they are consumed. Service provider : Federal or local government agencies, or one of the licensed

    -- 1 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 2 private sector establishments, concerned with the distribution and supplying of electricity to consumers. Person : Natural or legal person. Producer : Any person who produces electricity using the distributed production unit, in accordance with the provisions of this Decree by Law and the legislation in force in the Emirate. This does not include the service provider. Distributed production unit : One or more units designated for the production of electricity by renewable energy sources, which are connected to the distribution network. Distribution network : The network of service provider, which consists, without limitation, of the electric power network with the voltage that lines, cables, substations, pole-mounted transformers, and analog electrical elements, such as resistors, inductors, capacitors, switches, and meters designated for distributing electricity to consumers. Connection : Connecting distributed production units to the distribution network. Connection agreement : The agreement between the service provider and the producer, which regulates the rules and conditions for the operation of the distributed production unit and its connection to the distribution network. Annual limi : The annual maximum limit of the distributed production units that are allowed to be connected with the service provider distribution network. Imported electric power : The electric power that is consumed by the producer and supplied from the distribution network by calculating the consumption allocated to measure the amount of electric energy imported from the distribution network to a specific real estate unit by one or more meters designated for this

    -- 2 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 3 purpose owned by the producer. Exported electric power : The electric power produced by the producer through the distributed production unit, which is exported to the distribution network. Renewable energy sources : Renewable natural resources that are used to produce electric power. Excess capacity : The difference between exported electric power and imported electric power during a specified period of time. Electrical installations contractors : The consultant qualified to design, supervise and follow up the connection process, or the electrical contractor qualified to install, maintain and connect the distributed production units to the distribution network.

  2. 2

    Article 2

    Article (2) Objectives of the Decree by Law This Decree by Law aims to: 1. Organise the connection of distributed production units to the distribution network and its specifications. 2. Enable people to produce electric power from renewable energy sources. 3. Enhance the diversification of renewable energy sources within the State with the aim of optimising the use of natural resources. 4. Contribute to protecting the environment by reducing carbon footprint. 5. Reduce the demand for electricity from the distribution networks during peak times.

  3. 3

    Article 3

    Article (3) Scope of Application The provisions of this Decree by Law shall apply to the operations of connecting distributed production units to the distribution network, and also to all producers, service providers, and electrical installations contractors in the State, including economic, free, and investment

    -- 3 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 4 zones.

  4. 4

    Article 4

    Article (4) Competences of the Ministry For the purposes of implementing this Decree by Law, the Ministry shall be responsible for the following: 1. Carry out the duties of the Competent Authority in the Emirates in which Etihad Water & Electricity, or any federal entity that takes its place, provides services. 2. Create a database of distributed production units and producers. 3. Coordinate with the local Competent Authorities and service providers regarding the implementation of the provisions of this Decree by Law.

  5. 5

    Article 5

    Article (5) Competencies of the Competent Authority For the purposes of implementing this Decree by Law, the Competent Authority shall assume, within its jurisdiction, and in accordance with the legislation, regulations, and powers in force in the State, the following competencies: 1. Prepare and approve the general policy for the production of electric power from the distributed production units. 2. Determine the electrical voltage, the size of the distributed production units that are allowed to be connected to the distribution network, and the renewable power sources licensed to be used for the production of distributed electric power in coordination with the service provider. 3. Adopt the annual limit and the mechanism for distributing it to different categories of producers in order to achieve the objectives of the general policy for the production of electric power from distributed production units in coordination with the service provider. 4. Adopt the terms, regulations, agreements, requirements, standards, and specifications of linking distributed production units, and conducting a periodic review of them to ensure the stability of the distribution network, in accordance with the standards and specifications approved in the concerned State and Emirate, in coordination with service

    -- 4 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 5 providers. 5. Monitor and supervise producers and verify their compliance with the provisions of this Decree by Law, conditions, regulations, agreements, requirements, standards, and specifications of connecting distributed production units, impose fines and administrative penalties, and take appropriate corrective measures in accordance with the provisions of this Decree by Law and the legislation in force in each emirate. 6. Create a database for producers that includes all data and information on the size of production capacity, production volume, and location and quality of distributed production units. 7. License the production of energy from distributed production units and connect them to the distribution network in accordance with the legislation in force in the State.

  6. 6

    Article 6

    Article (6) Service Provider Functions For the purposes of implementing this Decree by Law, service providers shall assume the following competencies: 1. Approve electrical installations contractors and ensure that they are fully aware of the requirements, specifications, and standards of distributed production units, the requirements for connecting them to the distribution network, and the risks of this connection to the stability of the network, in accordance with the specifications and technical requirements approved in each emirate. 2. Feed the database of the Ministry and the Competent Authority with the data of distributed production units and producers on a regular basis.

  7. 7

    Article 7

    Article (7) Connection agreement Any person wishing to connect the distributed production unit to the distribution network shall obtain prior approval from the Competent Authority and conclude the connection agreement with the service provider in accordance with the legislation in force at the Competent Authority.

    -- 5 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 6

  8. 8

    Article 8

    Article (8) Producer obligations The producer shall be committed to the following: 1. Obtain the approval of the Competent Authorities for licensing buildings and classifying land uses in the emirate before installing distributed production units and connecting them to the distribution network. 2. Contract with electrical installations contractors approved by the service provider. 3. Obtain a license from the Competent Authority for the production of electric power by distributed production units in accordance with the legislation in force at the Competent Authority. 4. Provide all requirements and devices necessary to install distributed production unit and connect them to the distribution network according to specifications, including security and safety requirements and electricity meters. 5. Comply with the terms of the connection agreement, all the requirements, conditions, and regulations of the connection, and any other conditions approved by the Competent Authority and the service provider in this regard. 6. Not exceeding the electric power limit that is allowed to be produced and exported to the distribution network. 7. Not doing any work that affects the safety and efficiency of the distribution network. 8. Cooperate with the employees of the Competent Authority and the service provider as to everything related to the provisions of this Decree by Law and the local legislation in force, including allowing them to measure the amount of exported electric power. 9. Preserve the environment, health, and public safety in accordance with the requirements of the legislation in force in this regard. 10. Pay the fees and costs of connecting distributed production units.

  9. 9

    Article 9

    Article (9) Consumption and export of the produced electric power The Competent Authority may regulate the tariff for supplying imported electric power,

    -- 6 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 7 exported electric power, excess capacity, fees, and costs for connecting distributed production units to different categories of producers, and adopt any material or non-material incentive systems, in line with the approved general policy for the production of electric power from distributed production units in the emirate.

  10. 10

    Article 10

    Article (10) Amend the terms of connection and its annual limit Without prejudice to the rights of the producers, the service provider, after obtaining the approval of the Competent Authority, may do the following: 1. Make the appropriate amendments to the terms of connection, provided that he shall announce these amendments and their effective date in accordance with the procedures determined by the Competent Authority. 2. Amend the annual connection limit, by increasing or decreasing it, to ensure the efficiency and safety of the distribution network and its related activities, and determining the priorities of the connection and the categories of targeted producers in accordance with the annual connection limit and the general policy for the production of electric power from distributed production units.

  11. 11

    Article 11

    Article (11) Distribution System Protection The service provider may, at any time, disconnect the distributed production unit from the distribution network if there is a danger threatening the security and safety of the distribution network or if the producer violates any of the connection requirements or the connection agreement, provided that the service provider shall notify the Competent Authority in this case.

  12. 12

    Article 12

    Article (12) Administrative Violations and Sanctions Violations and administrative penalties shall be defined for acts committed in violation of

    -- 7 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 8 the provisions of this Decree by Law and the resolutions issued in implementation thereof by the bodies that impose penalties and the mechanism of grievance, and the body concerned with collecting administrative fines, under a resolution issued by the Council of Ministers based on the proposal by the Minister and in coordination with the Competent Authority.

  13. 13

    Article 13

    Article (13) Delegation of competencies The Competent Authority may delegate any of its competencies stipulated in this Decree by Law and the resolutions issued in implementation thereof to the service provider, in accordance with the legislation in force.

  14. 14

    Article 14

    Article (14) Regularisation All producers and service providers shall regularise their status in accordance with the provisions of this Decree by Law within a maximum period of one year from the date of its enforcement, and the Competent Authority may extend this period for up to one year.

  15. 15

    Article 15

    Article (15) Executive Resolutions The Competent Authority shall issue the resolutions necessary to implement the provisions of this Decree by Law, each according to its competence.

  16. 16

    Article 16

    Article (16) Repeals Any provision that violates or contradicts the provisions of this Decree by Law shall be repealed.

    -- 8 of 9 --

    Federal Decree by Law No. (17) of 2022 Regulating the Connection of Renewable Energy Production Units Distributed on the Electrical Grid 9

  17. 17

    Article 17

    Article (17) Publication and Entry into Force of the Decree by Law This Decree by Law shall be published in the Official Gazette and shall enter into force thirty (30) days as of the date of its publication. Mohammed Bin Zayed Al Nahyan President of the United Arab Emirates, Issued by us at the Palace of the Presidency in Abu Dhabi: On: Safar 30, 1444 H Corresponding to: September 26, 2022

    -- 9 of 9 --

Note: The Arabic text of this legislation is the authoritative version as per the official UAE Legislation portal.

Articles in this law(17)
  1. 1Article (1) Definitions In application of the provisions of this Decree by Law,
  2. 2Article (2) Objectives of the Decree by Law This Decree by Law aims to: 1. Organ
  3. 3Article (3) Scope of Application The provisions of this Decree by Law shall appl
  4. 4Article (4) Competences of the Ministry For the purposes of implementing this De
  5. 5Article (5) Competencies of the Competent Authority For the purposes of implemen
  6. 6Article (6) Service Provider Functions For the purposes of implementing this Dec
  7. 7Article (7) Connection agreement Any person wishing to connect the distributed p
  8. 8Article (8) Producer obligations The producer shall be committed to the followin
  9. 9Article (9) Consumption and export of the produced electric power The Competent
  10. 10Article (10) Amend the terms of connection and its annual limit Without prejudic
  11. 11Article (11) Distribution System Protection The service provider may, at any tim
  12. 12Article (12) Administrative Violations and Sanctions Violations and administrati
  13. 13Article (13) Delegation of competencies The Competent Authority may delegate any
  14. 14Article (14) Regularisation All producers and service providers shall regularise
  15. 15Article (15) Executive Resolutions The Competent Authority shall issue the resol
  16. 16Article (16) Repeals Any provision that violates or contradicts the provisions o
  17. 17Article (17) Publication and Entry into Force of the Decree by Law This Decree b
Reading shortcut

Ask LEXAI a question about Federal Decree by Law No. (17) of 2022.

Plain-English answers, with a citation back to the exact article. Free to use, no sign-up.

LEXAI provides general legal information, not legal advice. For your specific case, speak to a licensed UAE lawyer.